Which role distributes FPTs during the Construction Phase?

Explanation:
Distributing functional performance tests during construction is handled by the Commissioning Team on site. The on‑site CxT takes the commissioning plan and breaks it into test packages, then assigns each test to the appropriate trades, schedules when tests will run, and ensures the tests are conducted and the results recorded. The CxA provides oversight and approval of the process, but the practical task of issuing and coordinating FPTs comes from the CxT. The Owner sets goals and acceptance criteria, and the Contractor supplies the field resources to carry out the tests under direction, but the actual distribution of FPTs is the CxT’s responsibility.

Distributing functional performance tests during construction is handled by the Commissioning Team on site. The on‑site CxT takes the commissioning plan and breaks it into test packages, then assigns each test to the appropriate trades, schedules when tests will run, and ensures the tests are conducted and the results recorded. The CxA provides oversight and approval of the process, but the practical task of issuing and coordinating FPTs comes from the CxT. The Owner sets goals and acceptance criteria, and the Contractor supplies the field resources to carry out the tests under direction, but the actual distribution of FPTs is the CxT’s responsibility.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy